The Swedish Maritime Administration has awarded a joint venture of Boskalis Sweden AB, Van Oord Sweden AB and Rohde Nielsen A/S the contract to deepen and widen the fairway to the Port of Gothenburg.
The award is an important step in the Skandia Gateway project, which will allow today’s largest container vessels to be received fully laden, and even larger vessels in future.
The depth of the fairway currently limits how much cargo the largest container vessels can carry to and from Gothenburg, the largest port in the Nordic region.
The contract covers dredging of about 7 million cubic metres of loose material and rock and adaptation of the fairway markings, making it one of the largest dredging projects in Sweden.
Fairway work is due to start in August 2027, and the whole project is expected to be complete in autumn 2028, when the port will be able to receive vessels with a draft of 16.5 metres, compared with 13.5 metres today.
An option in the contract allows the port to order further deepening for drafts of up to 17.5 metres.
The base contract is worth approximately SEK 2.3 billion, with the possibility of additional work through agreed options.
Signing between the Swedish Maritime Administration, the Gothenburg Port Authority and the joint venture is planned for the end of 2026, provided the award is not legally challenged.
After the previous procurement was cancelled in autumn 2025, the project optimised the fairway design and reduced the scope of dredging. Meanwhile quayside work has continued under the port’s management: the quay reinforcement is complete and separate dredging close to the quay is under way.
Elin Dörrheide, Project Manager for Skandia Gateway at the Port of Gothenburg, said the project is progressing as planned and that rising cargo volumes, deeper-draft vessels and long-term congestion in other major European ports keep the deepening strategically vital.
Thomas Nord, Head of Unit at the Swedish Maritime Administration, said the measures will let the largest container vessels carry more cargo to and from Gothenburg, strengthening access to efficient maritime transport and Sweden’s competitiveness.